Transcoding Removal Progress Tracking
Project Overview
Complete removal of server-side transcoding functionality and implementation of local video player fallback system.
Current Status: 📋 PLANNING PHASE
Executive Summary
- Total Tasks: 23
- Completed: 0
- In Progress: 0
- Pending: 23
- Blocked: 0
Phase Progress
Phase 1: API Modifications ✅ COMPLETED
Status: Completed | Completion Date: [Current Date]
- API-001: Disable transcoding endpoint
- API-002: Remove transcoding redirect logic
- API-003: Create direct streaming endpoint (Enhanced existing endpoint)
Phase 2: Format Detection 🔴 CRITICAL
Status: Not Started | Deadline: Week 1
- FORMAT-001: Redesign format detection logic
- FORMAT-002: Update format type definitions
Phase 3: UI Components 🟡 HIGH PRIORITY
Status: Not Started | Deadline: Week 2
- UI-001: Create local player launcher component
- UI-002: Update video card indicators
- UI-003: Modify unified video player
Phase 4: Player Launch System 🟡 HIGH PRIORITY
Status: Not Started | Deadline: Week 2
- LAUNCH-001: Cross-platform launch logic
- LAUNCH-002: Player availability detection
Phase 5: Settings & Preferences 🟢 MEDIUM PRIORITY
Status: Ready for Implementation | Deadline: Week 3
- SETTINGS-001: Local player preferences UI
- SETTINGS-002: Preference persistence
Phase 6: Cleanup & Optimization 🟢 LOW PRIORITY
Status: Ready for Implementation | Deadline: Week 4
- CLEANUP-001: Remove transcoding dependencies
- CLEANUP-002: Update package.json
- CLEANUP-003: Documentation update
Testing & Validation 🔴 REQUIRED
Status: Ready for Implementation | Deadline: Ongoing
- TEST-001: Unit test suite
- TEST-002: Integration testing
Detailed Task Status
Critical Path Tasks (Must Complete First)
| Task ID | Description | Status | Assignee | Start Date | Due Date | Notes |
|---|---|---|---|---|---|---|
| API-001 | Disable transcoding endpoint | ⏳ Pending | TBD | - | - | Critical path blocker |
| API-002 | Remove transcoding redirect | ⏳ Pending | TBD | - | - | Depends on API-001 |
| FORMAT-001 | Redesign format detection | ⏳ Pending | TBD | - | - | Depends on API-002 |
| UI-001 | Create launcher component | ⏳ Pending | TBD | - | - | Depends on FORMAT-001 |
Risk Assessment
🔴 High Risk Tasks
- API-001/002: Critical path - affects all video playback
- FORMAT-001: Core logic change with widespread impact
- LAUNCH-001: Platform compatibility complexity
🟡 Medium Risk Tasks
- UI-001: Complex component with multiple states
- TEST-001: Comprehensive testing required
- SETTINGS-001: UI integration complexity
🟢 Low Risk Tasks
- CLEANUP tasks: Non-critical path items
- Documentation: Can be done post-deployment
- UI-002: Simple visual updates
Daily Progress Updates
Date: [Update Daily]
Completed Today:
- Task X - Brief description
- Task Y - Brief description
In Progress:
- Task Z - Current status/blockers
Blockers/Issues:
- Issue description and impact
- Proposed solution/timeline
Plan for Tomorrow:
- Task A - Priority reason
- Task B - Dependencies
Weekly Milestones
Week 1: Foundation (Days 1-7)
Goal: Complete API modifications and format detection Target Completion: 5/23 tasks (22%)
Deliverables:
- All API endpoints return proper responses
- Format detection logic updated
- No transcoding code paths remain active
Success Criteria:
- Unsupported formats show appropriate messages
- Direct streaming works for supported formats
- No server CPU usage for transcoding
Week 2: User Interface (Days 8-14)
Goal: Complete UI components and player launch system Target Completion: 11/23 tasks (48%)
Deliverables:
- Local player launcher component functional
- Video cards show format indicators
- Player launch works on major platforms
Success Criteria:
- Users can launch videos in local players
- UI is intuitive and responsive
- Cross-platform compatibility verified
Week 3: Settings & Polish (Days 15-21)
Goal: Complete settings system and optimization Target Completion: 16/23 tasks (70%)
Deliverables:
- Settings panel with player preferences
- Preference persistence working
- Performance optimizations complete
Success Criteria:
- Users can customize player behavior
- Settings persist across sessions
- Performance meets requirements
Week 4: Cleanup & Launch (Days 22-28)
Goal: Complete cleanup, testing, and deployment Target Completion: 23/23 tasks (100%)
Deliverables:
- All transcoding code removed
- Documentation updated
- Testing complete and passing
Success Criteria:
- Zero transcoding functionality remains
- All tests pass
- Documentation is comprehensive
- Ready for production deployment
Quality Metrics
Code Quality
- Test Coverage Target: 90%+
- TypeScript Strict Mode: Enabled
- ESLint Issues: 0
- Build Warnings: 0
Performance Metrics
- Server CPU Usage: 0% for video playback
- Player Launch Time: < 2 seconds
- Memory Usage: Reduced vs transcoding
- Response Time: < 100ms for API calls
User Experience
- Task Success Rate: 95%+
- User Satisfaction: 4.5/5+
- Error Rate: < 1%
- Support Tickets: < 5% increase
Communication Plan
Stakeholder Updates
Frequency: Weekly on Fridays Recipients: Development team, project stakeholders Format: Email + project dashboard
Issue Escalation
Level 1: Team lead (within 4 hours) Level 2: Project manager (within 8 hours) Level 3: Executive sponsor (within 24 hours)
Documentation Updates
- Technical docs: Updated with each completed task
- User documentation: Completed by Week 3
- API documentation: Updated by Week 1
Rollback Procedures
Emergency Rollback
Trigger: Critical functionality broken Timeline: Within 2 hours Process:
- Disable new features via feature flag
- Restore transcoding endpoints
- Revert format detection logic
- Notify stakeholders
Planned Rollback
Trigger: Insufficient user adoption Timeline: Within 1 week Process:
- Feature flag gradual rollout reversal
- User communication campaign
- Data migration if needed
- Post-mortem analysis
Success Celebration 🎉
Completion Target: All 23 tasks completed and tested Celebration Plan: Team recognition + project retrospective Learning Documentation: Share insights with broader team
Update Instructions
Daily: Update progress, blockers, and next steps Weekly: Update milestone progress and risk assessment As Needed: Add new tasks or modify existing ones
Last Updated: [Date] Next Update: [Date] Document Owner: [Name]